Analisa Satuan Harga Pekerjaan Plesteran Dan Acian

Posted on


 



Pasir Pasang per m3
220.000,-
Semen per sak 50 kg  72.000,-
Harga Upah Pekerja per hari 70.000,-
Harga Upah Tukang Batu per hari  100.000,-
Harga Upah Kepala Tukang per hari 120.000,-
Harga Upah Mandor per hari 150.000,-
Pekerjaan Plesteran Adukan 1 : 2 tebal 2 cm / m2 
Material
Semen 0,240 sak @ 72.000 = 17.280
Pasir Pasang 0,014 m3 @ 220.000 = 3.080
Alat Bantu 1,000 Ls @ 2.500 = 2.500
Subtotal = 22.860
Upah
Pekerja 0,300 OH @ 70.000 = 21.000
Tukang Batu 0,150 OH @ 100.000 = 15.000
Kepala Tukang 0,020 OH @ 120.000 = 2.400
Mandor 0,010 OH @ 150.000 = 1.500
 Subtotal = 39.900
 Total = 62.760
Dibulatkan = 62.700
Pekerjaan Plesteran Adukan 1 : 3 tebal 2 cm / m2 
Material
Semen 0,180 sak @ 72.000 = 12.960
Pasir Pasang 0,016 m3 @ 220.000 = 3.520
Alat Bantu 1,000 Ls @ 2.500 = 2.500
Subtotal = 18.980
Upah
Pekerja 0,300 OH @ 70.000 = 21.000
Tukang Batu 0,150 OH @ 100.000 = 15.000
Kepala Tukang 0,020 OH @ 120.000 = 2.400
Mandor 0,010 OH @ 150.000 = 1.500
 Subtotal = 39.900
 Total = 58.880
Dibulatkan = 58.800
Pekerjaan Plesteran Adukan 1 : 4 tebal 2 cm / m2 
Material
Semen 0,145 sak @ 72.000 = 10.440
Pasir Pasang 0,018 m3 @ 220.000 = 3.960
Alat Bantu 1,000 Ls @ 2.500 = 2.500
Subtotal = 16.900
Upah
Pekerja 0,300 OH @ 70.000 = 21.000
Tukang Batu 0,150 OH @ 100.000 = 15.000
Kepala Tukang 0,020 OH @ 120.000 = 2.400
Mandor 0,010 OH @ 150.000 = 1.500
 Subtotal = 39.900
 Total = 56.800
Dibulatkan = 56.800
Pekerjaan Plesteran Adukan 1 : 5 tebal 2 cm / m2 
Material
Semen 0,120 sak @ 72.000 = 8.640
Pasir Pasang 0,020 m3 @ 220.000 = 4.400
Alat Bantu 1,000 Ls @ 2.500 = 2.500
Subtotal = 15.540
Upah
Pekerja 0,300 OH @ 70.000 = 21.000
Tukang Batu 0,150 OH @ 100.000 = 15.000
Kepala Tukang 0,020 OH @ 120.000 = 2.400
Mandor 0,010 OH @ 150.000 = 1.500
 Subtotal = 39.900
 Total = 55.440
Dibulatkan = 55.400

Pekerjaan Acian / m2 

Material
Semen 0,035 sak @ 72.000 = 2.520
Alat Bantu 1,000 Ls @ 200 = 200
Subtotal = 2.720
Upah
Pekerja 0,200 OH @ 70.000 = 14.000
Tukang Batu 0,100 OH @ 100.000 = 10.000
Kepala Tukang 0,010 OH @ 120.000 = 1.200
Mandor 0,010 OH @ 150.000 = 1.500
 Subtotal = 26.700
 Total = 29.420
Dibulatkan = 29.400

Baca juga: Warna Cat Dinding / Tembok Kamar Tidur

Bisa dilihat bahwa untuk pekerjaan plester aci hanya perlu ditambahkan antara biaya plesteran dan acian. Seperti misalnya plesteran adukan 1 pc : 5 ps biaya 65.400 + acian 39.400 = 104.800.

Leave a Reply