Pasir Pasang per m3
|
220.000,- |
Semen per sak 50 kg | 72.000,- |
Harga Upah Pekerja per hari | 70.000,- |
Harga Upah Tukang Batu per hari | 100.000,- |
Harga Upah Kepala Tukang per hari | 120.000,- |
Harga Upah Mandor per hari | 150.000,- |
Pekerjaan Plesteran Adukan 1 : 2 tebal 2 cm / m2
Material | ||||||
Semen | 0,240 | sak | @ | 72.000 | = | 17.280 |
Pasir Pasang | 0,014 | m3 | @ | 220.000 | = | 3.080 |
Alat Bantu | 1,000 | Ls | @ | 2.500 | = | 2.500 |
Subtotal | = | 22.860 | ||||
Upah | ||||||
Pekerja | 0,300 | OH | @ | 70.000 | = | 21.000 |
Tukang Batu | 0,150 | OH | @ | 100.000 | = | 15.000 |
Kepala Tukang | 0,020 | OH | @ | 120.000 | = | 2.400 |
Mandor | 0,010 | OH | @ | 150.000 | = | 1.500 |
Subtotal | = | 39.900 | ||||
Total | = | 62.760 | ||||
Dibulatkan | = | 62.700 |
Pekerjaan Plesteran Adukan 1 : 3 tebal 2 cm / m2
Material | ||||||
Semen | 0,180 | sak | @ | 72.000 | = | 12.960 |
Pasir Pasang | 0,016 | m3 | @ | 220.000 | = | 3.520 |
Alat Bantu | 1,000 | Ls | @ | 2.500 | = | 2.500 |
Subtotal | = | 18.980 | ||||
Upah | ||||||
Pekerja | 0,300 | OH | @ | 70.000 | = | 21.000 |
Tukang Batu | 0,150 | OH | @ | 100.000 | = | 15.000 |
Kepala Tukang | 0,020 | OH | @ | 120.000 | = | 2.400 |
Mandor | 0,010 | OH | @ | 150.000 | = | 1.500 |
Subtotal | = | 39.900 | ||||
Total | = | 58.880 | ||||
Dibulatkan | = | 58.800 |
Pekerjaan Plesteran Adukan 1 : 4 tebal 2 cm / m2
Material | ||||||
Semen | 0,145 | sak | @ | 72.000 | = | 10.440 |
Pasir Pasang | 0,018 | m3 | @ | 220.000 | = | 3.960 |
Alat Bantu | 1,000 | Ls | @ | 2.500 | = | 2.500 |
Subtotal | = | 16.900 | ||||
Upah | ||||||
Pekerja | 0,300 | OH | @ | 70.000 | = | 21.000 |
Tukang Batu | 0,150 | OH | @ | 100.000 | = | 15.000 |
Kepala Tukang | 0,020 | OH | @ | 120.000 | = | 2.400 |
Mandor | 0,010 | OH | @ | 150.000 | = | 1.500 |
Subtotal | = | 39.900 | ||||
Total | = | 56.800 | ||||
Dibulatkan | = | 56.800 |
Pekerjaan Plesteran Adukan 1 : 5 tebal 2 cm / m2
Material | ||||||
Semen | 0,120 | sak | @ | 72.000 | = | 8.640 |
Pasir Pasang | 0,020 | m3 | @ | 220.000 | = | 4.400 |
Alat Bantu | 1,000 | Ls | @ | 2.500 | = | 2.500 |
Subtotal | = | 15.540 | ||||
Upah | ||||||
Pekerja | 0,300 | OH | @ | 70.000 | = | 21.000 |
Tukang Batu | 0,150 | OH | @ | 100.000 | = | 15.000 |
Kepala Tukang | 0,020 | OH | @ | 120.000 | = | 2.400 |
Mandor | 0,010 | OH | @ | 150.000 | = | 1.500 |
Subtotal | = | 39.900 | ||||
Total | = | 55.440 | ||||
Dibulatkan | = | 55.400 |
Pekerjaan Acian / m2
Material | ||||||
Semen | 0,035 | sak | @ | 72.000 | = | 2.520 |
Alat Bantu | 1,000 | Ls | @ | 200 | = | 200 |
Subtotal | = | 2.720 | ||||
Upah | ||||||
Pekerja | 0,200 | OH | @ | 70.000 | = | 14.000 |
Tukang Batu | 0,100 | OH | @ | 100.000 | = | 10.000 |
Kepala Tukang | 0,010 | OH | @ | 120.000 | = | 1.200 |
Mandor | 0,010 | OH | @ | 150.000 | = | 1.500 |
Subtotal | = | 26.700 | ||||
Total | = | 29.420 | ||||
Dibulatkan | = | 29.400 |